First Notice | 2/17/2016 | 2/17/2016 | 2/21/2019 | | DONE |
Eric Story
|
|
|
This permit finaled on the web by Winters LLC
|
Final | 2/16/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Eric Story
|
|
|
Thank you! Phone #: ###-#### Inspection requested via web by Celinda Winters final on lab ok
|
Electrical Rough-In | 2/8/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Rex Boyles
|
|
|
ceiling inspection Phone #: ###-#### Inspection requested via web by Celinda Winters r/i molecular lab ceilings 100%
|
Electrical Rough-In | 1/18/2016 | 1/19/2016 | 1/19/2016 | A | PASS |
Rex Boyles
|
|
|
Ceiling inspection please Phone #: ###-#### Inspection requested via web by Celinda Winters r/i ceilings ok in molecular lab
|
Conference | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | DONE |
Rex Boyles
|
|
|
Early afternoon please. This morning if possible would be helpful. Thank you Phone #: ###-#### Inspection requested via web by Celinda Winters discuss existing electrical and data in new ceilings. Will keep cabling up off grid and install ko seals and support where necessary. Will demo abandonded conduits.
|
Electrical Rough-In | 12/17/2015 | 12/18/2015 | 12/18/2015 | A | PASS |
Rex Boyles
|
|
|
Later morning if possible Thank you Phone #: ###-#### Inspection requested via web by Celinda Winters r/i molecular walls ok
|
Issue PAID IN FULL permit | | | 11/2/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 11/2/2015 | | |
|
|
|
|
Application received | | | 11/2/2015 | | DONE |
|
|
|
This permit was created on the web by Celinda Winters
|