Final | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt final ok
|
Final | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt Corrections made. Final ok
|
Final | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | FAIL |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt 250.8 A 6 GFCI protection required on kitchen receps. (island)
|
Electrical Rough-In | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
Eric Story
|
|
|
Installing heat matt in concrete at 9:00 am Phone #: ###-#### Inspection requested via web by John VanZandt drive way heated mats ok cover(cold leads shall be installed in conduit to juction box)
|
Electrical Rough-In | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | PASS |
Eric Story
|
|
|
Floor heat utility and hall Phone #: ###-#### Inspection requested via web by John VanZandt utility and hall floor heat ok cover
|
Final | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | CANC |
Eric Story
|
|
|
Floor heat mst bath, conduit dept Insp driveway Phone #: ###-#### Inspection requested via web by John VanZandt needed a rough-in inspection
|
Electrical Rough-In | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Eric Story
|
|
|
Floor heat mst bath, conduit dept Insp driveway Phone #: ###-#### Inspection requested via web by John VanZandt master bath floor heat and underground across garage driveway ok cover
|
Electrical Rough-In | 3/16/2016 | 3/16/2016 | 3/16/2016 | A | PASS |
Eric Story
|
|
|
Bath floor heat Phone #: ###-#### Inspection requested via web by John VanZandt back bathrooms floor heat ok cover
|
Electrical Rough-In | 2/16/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Eric Story
|
|
|
entry cable heat ok cover
|
Final | 2/15/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Eric Story
|
|
|
Installing concrete heat matt, pouring at 9:30 am. Phone #: ###-#### Inspection requested via web by John VanZandt entry heated cable ok cover
|
Change Status to I | | | 2/16/2016 | | DONE |
|
|
|
as per Eric S was ffinaled by mistake
|
Final | 1/11/2016 | 1/11/2016 | 1/11/2016 | P | CANC |
Rock A. Hudson
|
|
|
Soffet light insp Phone #: ###-#### Inspection requested via web by John VanZandt Needed rough in inspection for soffits.
|
Electrical Rough-In | 1/11/2016 | 1/11/2016 | 1/11/2016 | P | PASS |
Rock A. Hudson
|
|
|
Soffet light insp Phone #: ###-#### Inspection requested via web by John VanZandt All soffit lights have been changed to standard 3/0 light boxes 2 hr fire rated. 1 14-2 stubbed on soffit towards front of garage by meter base. Soffit rough in ok cover
|
Rough-In Permanent Service | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt soofits not allowed to cover until 2hr fire rating is confirmed rough-in ok cover p/s u/g n ok
|
Issue PAID IN FULL permit | | | 12/29/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/28/2015 | | DONE |
|
|
|
This permit was created on the web by John VanZandt
|