First Notice | 10/31/2016 | 10/31/2016 | 11/1/2016 | | DONE |
Eric Story
|
|
|
This permit finaled on the web by Debby Pierce
|
Final | 10/31/2016 | 10/31/2016 | 10/31/2016 | A | PASS |
Eric Story
|
|
|
Final. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Could not locate sign off sheet, Final ok
|
First Notice | 7/20/2016 | 7/20/2016 | 10/28/2016 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Debby Pierce
|
Electrical Rough-In | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Rock A. Hudson
|
|
|
TCO walk for VRT level. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Ramp lights (6) trims on back order with no exposed wiring. caulking when complete. Verify fusing on 480 v AC units. Temp occupy ok. Signed core and shell sheet for TRV TI only place to sign.
|
Electrical Rough-In | 9/27/2016 | 9/28/2016 | 9/28/2016 | A | PART |
Rock A. Hudson
|
|
|
TCO walk for VRT level to reinspect previous items. Later in the morning if possible. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Items still needed. 300.15- Junction box covers shall be installed, southend ceiling, north electrical rm. Ramp lights on wall 6 are back ordered, boxes open with no exposed wiring. Shall caulk and seal from moisture. Lamps required in bathrooms back in stool areas very dark. 440.4- Fusing for AC unit still need 480 volt units fused correctly.
|
Electrical Rough-In | 9/26/2016 | 9/26/2016 | 9/26/2016 | A | FAIL |
Rock A. Hudson
|
|
|
Pre TCO walk. Contact is Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Too many for formal notes. Exit ramp wall lights not complete. Complete fire pack mech. rm ceiling. Lighting not complete east bus loop. Covers required for all boxes low volt. Complete lighting on bus entry ramp. J-box covers south end and electrical rm. Bath occ sensors and can lamps. Server room s/l MC jacket broken. Service receptacle required 35' ofN. ACs. Verify all fusing for AC units. Low volt box open on VRT main level entry.
|
Electrical Rough-In | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling cover inspection VRT level. Contact Eric Gibson ###-####. If he does not answer contact Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves VRT grid complete rough in ok cover
|
Electrical Rough-In | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Rock A. Hudson
|
|
|
Reinspect for earthquake clips on F2 fixtures. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves
passed as noted on contractor print
|
Electrical Rough-In | 9/11/2016 | 9/12/2016 | 9/12/2016 | P | PASS |
Rock A. Hudson
|
|
|
Partial ceiling cover inspection. Contact is Eric Gibson ###-####. If he doesn''t answer contact Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves As noted on contractor print basement grid rough in ok cover. Will check TVR lobby luminaires earthquake clips next trip
|
Electrical Rough-In | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PART |
Rock A. Hudson
|
|
|
Partial ceiling cover inspection. Contact is Eric Gibson ###-####. If he doesn''t answer call Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Leave north end open for fire seal hole in upper floor. As noted on print center area grid rough in ok cover
|
Electrical Rough-In | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection bathroom entry. Wall roughin for cover. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves VRT entry hardlid, bathroom hardlid and lost and found wall rough in ok cover
|
Electrical Rough-In | 8/19/2016 | 8/19/2016 | 8/19/2016 | A | PASS |
Rock A. Hudson
|
|
|
Wall rough in inspection. Stair 5 VRT level. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Stair 5 walls for 1A and 1B and area A in lower level, both sides in A, also main level south wall in lobbynear stair 5 rough in ok cover.
|
Electrical Rough-In | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | PART |
Rock A. Hudson
|
|
|
Ceiling rough in men''s and women''s restrooms. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves west bath and janitors closet ceiling rough in ok cover. 440.14- Access is off set from under unit in east bath and ceiling not strong enough for persons weight. Move access under or inline with unit.
|
Change Status to I | | | 8/15/2016 | | DONE |
|
|
|
as per Rock-was issued by mistake-changed back to iss
|
Final | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Rock A. Hudson
|
|
|
Remainder of wall rough in inspection for VRT walls. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves South 1/2 wall rough in ok cover
|
Electrical Rough-In | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Rock A. Hudson
|
|
|
Wall rough in inspection for cover. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Basement north of concrete dividing wall rough in ok cover
|
Issue PAID IN FULL permit | | | 1/18/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 1/18/2016 | | |
|
|
|
|
Application received | | | 1/18/2016 | | DONE |
|
|
|
This permit was created on the web by Debby Pierce
|