Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberELE16-00506
StatusFinaled
Name ENTERPRISE ELECTRIC
Site Address 400 S CAPITOL BLVD
Project Name 
Customer NumberC-16001
ePlanReviewNo
Description
New: Underground phase of electrical.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  12/1/2016 PASS
DetailsDaryl DeGrange
as per Daryl DeGrange-all inspections have been done and permit is now complete so doc final
Electrical Rough-In11/23/201611/23/201611/23/2016PCANC
DetailsEric Story
We are requesting a rough-in inspection for stair 1, level 10 for this afternoon. Our contact onsite is Nic @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Wrong permit #
Final9/15/20169/16/20169/16/2016ACANC
DetailsEric Story
closing off the electrical
waiting for inspections to be moved to proper permit
Electrical Rough-In7/21/20167/21/20167/21/2016APASS
DetailsRock A. Hudson
We are requesting an underground inspection in the Alley way for this afternoon. Our contact onsite is Bobby ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate
Where 90s leave footing not to depth so will encase in concrete and per 300.5. South 1/2 of alley underground rough in ok cover
Electrical Rough-In4/20/20164/21/20164/21/2016PPASS
DetailsRex Boyles
We are requesting an electrical underground inspection for the main electrical room for tomorrow 4/21 in the afternoon. Our contact is Tony @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i u.slab 100% including stairwell 3 see e sheets
Electrical Rough-In4/19/20164/19/20164/19/2016PPASS
DetailsRex Boyles
We are requesting a main electrical underground inspection for the electrical room for this afternoon. Our contacts are Tony @ ###-#### or Bobby @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok continue underslab up to electrical room
Electrical Rough-In4/1/20164/1/20164/1/2016PPASS
DetailsDaryl DeGrange
We are requesting an underground inspection for the northwest area for this afternoon. Our contacts are Bobbie @ ###-#### or Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate rough-in ok cover UL Listed floor boxes and N.W. corner underground.
Electrical Rough-In3/23/20163/24/20163/24/2016PPASS
DetailsRex Boyles
We are requesting an additional inspection for stair tower 2 for tomorrow 3/24/16 in the afternoon. Our contacts are Bobbie @ ###-#### or Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate stairwell 2, north and west side conduit and boxes in walls r/i ok ALSO: Tony wants to know why they can't drive ground rods inside of bldg. to ground generator frame and they want to install nuecler exits in stairwell.
Electrical Rough-In3/23/20163/24/20163/24/2016APASS
DetailsRex Boyles
We are requesting a underground inspection for stair tower 2 for tomorrow 3/24/16 in the AM. Our contacts are Bobbie @ ###-#### or Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i stairwell 2 walls and north wall up to 4 foot ok NOTE;as of today look for inspector set in Big D trailer. See highlighted areas
Electrical Rough-In3/17/20163/18/20163/18/2016PPASS
DetailsRex Boyles
We are requesting an underground inspection for the east side of the elevator ground area for tomorrow 3/18/16 in the afternoon. Our contacts are Bobbie @ ###-#### or Tony @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i underslab at parking garage entry gates up to col. line 5 ok
Electrical Rough-In3/15/20163/16/20163/16/2016APASS
DetailsRex Boyles
We are requesting an underground inspection for the Generator room and from Column line 7 to column 5 for tomorrow 3/16/16 in the AM. Our onsite contact is Bobbie ###-#### or our Foreman Tony @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok underslab raceways in areas stated above
Electrical Rough-In3/3/20163/4/20163/4/2016PPASS
DetailsRex Boyles
We are requesting a rough-in inspection for stairwell 3 for tomorrow 3/4/16 in the afternoon. Our contact is Tony @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok up to 15' 3"(first pour) for conduit, boxes and sleeves
Conference3/3/20163/4/20163/4/2016ADONE
DetailsRex Boyles
We are requesting a conference with our inspector. Our contact is Tony ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate As per conversation with Tony on supply conductors to fire pump. NFPA 70 and 2014 NEC article 695.3(A)(1)-Electric utility service connection-A fire pump shall be permitted to be supplied by a separate service, or from a connection located ahead of and not within the same cabinet, enclosure, vertical switchgear section or vertical switchboard section as the service disconnecting means. The connection shall be located and arranged so as to minimize the possibility of damage by fire from within the premesis and from exposing hazards. 695.4(A)-Direct Connection-The "supply" conductors shall directly connect the power source to a listed fire pump controller.
Electrical Rough-In3/3/20163/4/20163/4/2016APASS
DetailsRex Boyles
We are requesting a rough-in inspection for stairwell 3 for tomorrow 3/4/16 in the am. Our contact is Tony @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok sleeves and heater raceways and box in form pour
Electrical Rough-In3/3/20163/3/20163/3/2016PPASS
DetailsRex Boyles
We are requesting an underground inspection for today in the afternoon. Our contact is Tony @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i underslab raceways from grid line 7 to the south 100% ok to cover
Electrical Rough-In2/26/20162/26/20162/26/2016PPASS
DetailsRex Boyles
We are requesting a inspection of the crane we just hooked up. Our contact is Tony @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate r/i u.ground, disconnect concrete encased electrode and feeder to crane ok
Electrical Rough-In2/19/20162/19/20162/19/2016PPASS
DetailsRex Boyles
Underground inspection Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok u.ground conduits and stub ups at southeast corner stairwell #1 and fire pump room ok
Issue PAID IN FULL permit  2/19/2016 DONE
Payment received via Govolutions
Application received  2/19/2016 DONE
This permit was created on the web by Clint Tate