ELE-Aging Inspection | 3/6/2019 | 3/6/2019 | 3/6/2019 | | PASS |
Mark Moncarr
|
|
|
This inspection was for RI only of future solar install. Drove by, no solar installed. If solar is installed, it will require a new permit to be pulled.
|
Final | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | PASS |
Mark Moncarr
|
|
|
Alt Energy Ok final. RI only was done for future solar installation. If solar is installed, and new permit must be pulled.
|
Final | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | CANC |
Eric Story
|
|
|
Inspecting our Solar Rough In Conduit. It runs from roof mounted junction box to exterior mounted pvc junction.
Call if you have questions. Phone #: ###-#### Inspection requested via web by Matthew Dunay
|
Electrical Rough-In | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | PASS |
Eric Story
|
|
|
Inspecting our Solar Rough In Conduit. It runs from roof mounted junction box to exterior mounted pvc junction.
Call if you have questions. Phone #: ###-#### Inspection requested via web by Matthew Dunay solar array conduit run ok cover
|
Issue PAID IN FULL permit | | | 5/4/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/4/2016 | | DONE |
|
|
|
This permit was created on the web by Matthew Dunay
|