Permit Information
Permit NumberELE16-01483
StatusFinaled
Name TASKER ELECTRICAL CONSTRUCTION INC
Site Address 2967 W CRESCENT RIM DR
Project NameCRESCENT RIM BUILDING # 4
Customer Number 
ePlanReviewNo
Description
Addition: feeders and branch circuits for 19 condos and fire alarm system.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice3/16/20183/16/20183/21/2018 DONE
DetailsEric Story
This permit finaled on the web by Stacie Tasker
Final3/16/20183/16/20183/16/2018PPASS
DetailsEric Story
Final sign off
Correction fixed, both cards have been signed and finaled electric permit
Final3/14/20183/15/20183/15/2018AFAIL
DetailsEric Story
Kenny is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker
AFCI protection for guest bedroom
Final12/29/201712/29/201712/29/2017PPART
DetailsEric Story
We need final inspections for the following units: 208, 301, 304.
Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Rooms as noted on request ok to occupy
Final12/7/201712/7/201712/7/2017PPART
DetailsEric Story
We need a final for Units 303, 101, 102, 107,201, 202, 207,. Kenny is the site contact Phone #: ###-#### Inspection requested via web by Stacie Tasker
temp occ for rooms as needed in inspection request temp occ ok
Final10/24/201710/25/201710/25/2017APART
DetailsEric Story
Core and shll temp occ inspection
Core and shell temp occ ok
Signed all necessary cards for this inspection
Final10/19/201710/20/201710/20/2017PCANC
DetailsEric Story
We need a temp occupancy final on the core ; shell. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Core and shell not ready
Final10/16/201710/17/201710/17/2017APART
DetailsEric Story
PArtial final for north units
North corridors and unit 302,203,206,205,204,106,105,104,103 in north end onlyok to occupy. South end to be inspected on another date...
Final10/13/201710/16/201710/16/2017PFAIL
DetailsEric Story
We need a final for All corridors and the Units on the North Side.
Thank you!
Phone #: ###-#### Inspection requested via web by Stacie Tasker
GFCI protection with receptacles within 6' of a sink misc areas
Lockouts for hard wired applainces misc thru out
Electrical Rough-In10/10/201710/11/201710/11/2017APASS
DetailsRock A. Hudson
We need a ceiling cover for the entire 3rd floor. Phone #: ###-#### Inspection requested via web by Stacie Tasker
Area noted grid rough in ok cover
Electrical Rough-In10/10/201710/10/201710/10/2017PPASS
DetailsRock A. Hudson
We need an fire alarm inspection for the electrical part of the fire alarm. On site Contact is Greg. Phone #: ###-#### Inspection requested via web by Stacie Tasker
Area noted rough in ok
Electrical Rough-In10/6/201710/6/201710/6/2017PPASS
DetailsEric Story
Ceiling cover for 2nd floor corridor. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
2nd floor corridor drop ceilings ok to cover
Electrical Rough-In10/3/201710/4/201710/4/2017PPASS
DetailsEric Story
We need a ceiling cover for 1st floor corridor. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
1st floor corridor ok to cover
Electrical Rough-In7/27/20177/28/20177/28/2017APASS
DetailsEric Story
Inspect floor heat in master bath
Master bath floor heat ok cover
Electrical Rough-In7/26/20177/27/20177/27/2017PPASS
DetailsEric Story
We need an inspection in Unit #302 for floor heat. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Main bath only ok cover, will look at master on another date...
Electrical Rough-In7/12/20177/13/20177/13/2017PPASS
DetailsEric Story
We need a softitt inspection for 1st floor corridor. Phone #: ###-#### Inspection requested via web by Stacie Tasker
1st floor corridor hard lids ok cover
Electrical Rough-In6/26/20176/27/20176/27/2017APASS
DetailsEric Story
We need a inspection for 2nd floor corridor. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker
2nd floor corridor hard lid soffits ok cover
Permanent Service5/31/20176/1/20176/1/2017APASS
DetailsEric Story
Kenny is site contact. We need service inspection for the following units:
103, 104, 105, 106, 203, 204, 205, 206 Phone #: ###-#### Inspection requested via web by Stacie Tasker
Service ok to energize, p/s u/g rec ok 19 meters needed
Electrical Rough-In5/11/20175/12/20175/12/2017APASS
DetailsEric Story
We need a 3rd floor corridor soffit, please! Phone #: ###-#### Inspection requested via web by Stacie Tasker
3rd floor soffits in hallways and lobby ok cover
Electrical Rough-In4/13/20174/13/20174/13/2017PPASS
DetailsEric Story
We need a soffit inspection for Units 101 ; 107.Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
units 101,107 soffits ok cover
Electrical Rough-In4/5/20174/5/20174/5/2017PPASS
DetailsEric Story
We need a soffit inspection for Units 304 ; 201. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Soffits in units 201,and 304 only ok cover
Electrical Rough-In3/30/20173/30/20173/30/2017PPASS
DetailsEric Story
We need a soffit inspection for Units 301 ;208. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
units 301,208 siffits ok cover
Electrical Rough-In3/21/20173/21/20173/21/2017PPASS
DetailsEric Story
we need a inspection for the 2nd floor utility closet and stairwell. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
2nd foor closet/storage and south stair ok cover
Electrical Rough-In3/17/20173/17/20173/17/2017PPASS
DetailsEric Story
We need a soffit inspection for Units 202 ; 207, please.
Thank you! Phone #: ###-#### Inspection requested via web by Stacie Units as requested hard lids ok cover
Electrical Rough-In3/9/20173/10/20173/10/2017PPASS
DetailsEric Story
We need a soffit inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Unit 301 hard lid ok cover
Electrical Rough-In3/6/20173/7/20173/7/2017APASS
DetailsEric Story
Corridor inspection
Unit 302 hard lids and elevator corridor hard lid ok cover
Electrical Rough-In3/6/20173/6/20173/6/2017PCANC
DetailsEric Story
We need an inspection for 3rd floor corridor and Unit 302 soffit. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
cancelling for tuesday
Electrical Rough-In3/6/20173/7/20173/6/2017ACANC
DetailsEric Story
We need an inspection for 3rd floor corridor and Unit 302 soffit. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Kenny ###-#### early morning if possible
Electrical Rough-In3/1/20173/1/20173/1/2017PPASS
DetailsRock A. Hudson
We need a wall cover on 1st ; 2nd floor corridor and a soffit inspection for Unit 102. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Area noted rough in ok cover
Electrical Rough-In2/17/20172/21/20172/21/2017APASS
DetailsEric Story
We need a soffit inspection for Units 203 ; 206. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Units as requested soffits ok cover
Electrical Rough-In2/15/20172/15/20172/15/2017PPASS
DetailsRock A. Hudson
We need a soffit inspection for Unit 204. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Area noted 204 soffits rough in ok cover
Electrical Rough-In1/25/20171/26/20171/26/2017APASS
DetailsEric Story
We need a soffit inspection for Unit 103. Contact is Kenny. Phone #: ###-#### Inspection requested via web by Stacie Tasker
Unit 103 soffits only ok cover
Electrical Rough-In1/20/20171/20/20171/20/2017PPASS
DetailsEric Story
We need a rough for the following units, 105, 107, 301. Site contact is Kenny Long. Phone #: ###-#### Inspection requested via web by Stacie Tasker
unit 105 hard lid @ units 101, 107 rough-in ok cover
Electrical Rough-In1/11/20171/11/20171/11/2017APASS
DetailsEric Story
We need soffits inspection for Units 104 ; 105 and s wall ; partial ceiling for Unit 304. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
unit304 ok cover units 101,104 and 106 hard lids ok cover
Electrical Rough-In1/3/20171/3/20171/3/2017PPASS
DetailsEric Story
We need a wall inspection for the following units: 101, 102, guest suite, ; 303. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Units as requested on inspection walls and hard lids ok cover
Electrical Rough-In12/22/201612/22/201612/22/2016PPASS
DetailsJames Ady
We need a wall rough for all of the 2nd floor on the South Side units. Kenny is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker 2nd floor Apartments South side only rough in ok
Final12/1/201612/2/201612/2/2016ACANC
DetailsEric Story
Unit 302 walls only
Needed rough-in
Electrical Rough-In12/2/201612/2/201612/2/2016PPASS
DetailsEric Story
Unit 302 walls only
Unit 302 walls and hard lids ok cover
Electrical Rough-In12/1/201612/1/201612/1/2016ACANC
DetailsEric Story
Unit 302 walls only
Scheduled wrong day
Electrical Rough-In12/1/201612/2/201612/1/2016ACANC
DetailsEric Story
Unit 302 walls only
Electrical Rough-In12/1/201612/1/201612/1/2016PNR
DetailsEric Story
WE need a wall rough for Unit 302 only. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Scheduled for wrong day, will create inspection for 12-2-2016
Electrical Rough-In11/18/201611/18/201611/18/2016PPASS
DetailsEric Story
We need a partial wall cover for all 3 floors on the north side. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
North rooms on floors 1st and 2nd floor panel walls only ok cover
Electrical Rough-In11/9/201611/10/201611/10/2016PPASS
DetailsEric Story
We need a ceiling inspection for the North side 1st ; 2nd floor. Kenny is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
rooms 130,106,203,206 walls and ceilings ok cover. Rooms inspected on the 11/9/16 ceilings ok cover
Electrical Rough-In11/8/201611/9/201611/9/2016PPASS
DetailsEric Story
We need a partial wall rough for North side for 1st, 2nd ; 3rd floors. Site contact is Kenny. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
1st and 2nd floor north rooms walls only ok cover
Electrical Rough-In9/27/20169/27/20169/27/2016PPASS
DetailsDaryl DeGrange
We need a ceiling inspection for the South Corridor. Site contact is Kenny.
Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker rough-in ok cover hard lid South Corridor ceiling
Electrical Rough-In9/20/20169/21/20169/21/2016PPASS
DetailsEric Story
We need a partial ceiling inspection for the North Half, 1st, 2nd, ; 3rd floor. Site contact is Kenny, ###-#### Phone #: ###-#### Inspection requested via web by Stacie Tasker
1st 2nd 3rd floor north side corridor hard lids only ok cover
Electrical Rough-In9/20/20169/20/20169/20/2016PCANC
DetailsEric Story
We need a partial ceiling on the 1st, 2nd, 3rd floor at the North Half. Site contact is Kenny, ###-####. Thank you! Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
Conference6/13/20166/14/20166/14/2016PDONE
DetailsRock A. Hudson
Please contact Greg 30 min prior to arrival. This is for a consultation. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker
Discussed the ampacity of feeders from basement to each unit. Quoted NEC 310.15(A)(2)exeption, if less than 10' or 10% of circuit length is enclosed by thermal insulation adjustment factor of using 60 degree column shall not apply. General contractor to assist with uninsulated path to help with costs of wiring.
Issue PAID IN FULL permit  5/9/2016 DONE
Payment received via Govolutions
Application received  5/9/2016 DONE
This permit was created on the web by Stacie Tasker