Final | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | PASS |
James Ady
|
|
|
2nd floor corridor Phone #: ###-#### Inspection requested via web by steve ragan Final ok
|
Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 | A | PART |
James Ady
|
|
|
Ceiling inspection in corridor where 2x2 troffers and can light frames are. Phone #: ###-#### Inspection requested via web by steve ragan ceilings ok to cover
|
Electrical Rough-In | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PASS |
Rock A. Hudson
|
|
|
2nd floor opposite the convention rooms. Asher Sears is the electrician onsite Phone #: ###-#### Inspection requested via web by steve ragan Asked contact to check weight rating of ceiling system and to research and assign ELE permit to BLD permit. Walls and hardlid rough in ok cover
|
Electrical Rough-In | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Rock A. Hudson
|
|
|
Asher Sears will be the electrician onsite. Phone #: ###-#### Inspection requested via web by steve ragan Corridor wall rough in ok cover
|
Issue PAID IN FULL permit | | | 5/11/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/11/2016 | | DONE |
|
|
|
This permit was created on the web by steve ragan
|
First Notice | 8/9/2016 | 8/9/2016 | | | |
James Ady
|
|
|
|