Print Statement | | | 8/30/2017 | | DONE |
|
|
|
sent 3rd late notice
|
First Notice | 5/8/2017 | 5/8/2017 | 6/16/2017 | | DONE |
James Ady
|
|
|
This permit finaled on the web by Clint Tate
|
First Notice | 7/15/2016 | 7/15/2016 | 6/16/2017 | | DONE |
James Ady
|
|
|
This permit finaled on the web by Clint Tate
|
Print Statement | | | 6/15/2017 | | DONE |
|
|
|
sent 2nd late notice
|
Final | 5/8/2017 | 5/8/2017 | 5/8/2017 | P | PASS |
James Ady
|
|
|
job complete,7/15/16 final ok
|
Print Statement | | | 4/20/2017 | | DONE |
|
|
|
sent 1st late final value
|
Print Statement | | | 11/21/2016 | | DONE |
|
|
|
|
Final | 7/14/2016 | 7/15/2016 | 7/15/2016 | P | PASS |
James Ady
|
|
|
We are requesting a final inspection for this project for tomorrow 7/15/16 in the afternoon. Our contact is Kory @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Final ok
|
Electrical Rough-In | 7/8/2016 | 7/11/2016 | 7/11/2016 | A | PASS |
James Ady
|
|
|
We are requesting a ceiling inspection for monday 7/11/16 in the am. Our contact is Kory @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate Ceiling only Ok to cover
|
Electrical Rough-In | 5/26/2016 | 5/27/2016 | 5/27/2016 | P | PASS |
James Ady
|
|
|
We are requesting a rough-in inspection for tomorrow 5/27/16 in the afternoon. Our contact is Kory @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Rough in main floor and hall only. ok to cover
|
Electrical Rough-In | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PASS |
James Ady
|
|
|
We are requesting a underground inspection for tomorrow morning 5/20/16. Our contact is Kory @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Underground ok to cover
|
Issue PAID IN FULL permit | | | 5/19/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/19/2016 | | DONE |
|
|
|
This permit was created on the web by Clint Tate
|