First Notice | 9/23/2016 | 9/23/2016 | 12/20/2016 | | DONE |
Mark Moncarr
|
|
|
|
Final | 9/21/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Mark Moncarr
|
|
|
Park restroom Phone #: ###-#### Inspection requested via web by Tye Thomas final ok
|
Permanent Service | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PASS |
Mark Moncarr
|
|
|
Service energize inspection Phone #: ###-#### Inspection requested via web by Tye Thomas p/s ug n ok
|
Conference | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | DONE |
James Ady
|
|
|
Scheduled Conference with James Ady at 10:30 A.M. on site Phone #: ###-#### Inspection requested via web by Tye Thomas Dicussed clerarance issues with panel location. Moving panel outside with a lockable door
|
Electrical Rough-In | 8/18/2016 | 8/18/2016 | 8/18/2016 | A | PASS |
James Ady
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Tye Thomas Check Panel Clearances inside building on final. Underground Between meter base and 480v panel ok to cover
|
Electrical Rough-In | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | PASS |
James Ady
|
|
|
Uffer Inspection Phone #: ###-#### Inspection requested via web by Tye Thomas Uffer only. Ok to cover
|
Issue PAID IN FULL permit | | | 6/29/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/29/2016 | | DONE |
|
|
|
This permit was created on the web by Tye Thomas
|