Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | A | PASS |
James Ady
|
|
|
Max Phone #: ###-#### Final ok
|
Electrical Rough-In | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PASS |
Eric Story
|
|
|
Max-ceiling Phone #: ###-####
ceiling grid ok to cover
|
Electrical Rough-In | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
James Ady
|
|
|
Max Phone #: ###-#### West wall server room ok to cover
|
Electrical Rough-In | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PASS |
Eric Story
|
|
|
Max Phone #: ###-#### walls as noted on print ok cover
|
Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PASS |
Eric Story
|
|
|
Mx Phone #: ###-#### panel wall only ok cover
|
Issue PAID IN FULL permit | | | 8/1/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/1/2016 | | DONE |
|
|
|
This permit was created on the web by Kevin Perez
|
First Notice | 9/30/2016 | 9/30/2016 | | | |
James Ady
|
|
|
|