First Notice | 10/11/2016 | 10/11/2016 | 8/30/2017 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Jesse Simpson
|
Electrical Rough-In | 10/10/2016 | 10/11/2016 | 10/11/2016 | A | PASS |
Rock A. Hudson
|
|
|
I forgot to pull my permit. Please review our Solar Rough In and Final out the permit. Call me if you would like me to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay Conduit installed for future solar install rough in ok cover
|
Final | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Rock A. Hudson
|
|
|
I forgot to pull my permit. Please review our Solar Rough In and Final out the permit. Call me if you would like me to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay Conduit installed from roof to west wall for future solar install. A seperate permit required when solar is installed. Final ok
|
Issue PAID IN FULL permit | | | 10/10/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/10/2016 | | DONE |
|
|
|
This permit was created on the web by Matthew Dunay
|