Final | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Tom Saunders
|
|
|
ceiling inspection, if carpet is complete i will have lenses in place and will be ready for final. Phone #: ###-#### Inspection requested via web by Thomas wilson....
work done...ok to final
|
Electrical Rough-In | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Tom Saunders
|
|
|
ceiling inspection, if carpet is complete i will have lenses in place and will be ready for final. Phone #: ###-#### Inspection requested via web by Thomas wilson...
ceiling ok to cover
|
Electrical Rough-In | 11/3/2016 | 11/3/2016 | 11/3/2016 | A | PASS |
Tom Saunders
|
|
|
this inspection is for the walls of the space. cieling and lights will be inspected in the future. Phone #: ###-#### Inspection requested via web by Thomas wilson.....rough ok to cover
|
Issue PAID IN FULL permit | | | 11/3/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/3/2016 | | DONE |
|
|
|
This permit was created on the web by Thomas wilson
|
First Notice | 11/29/2016 | 11/29/2016 | | | |
Tom Saunders
|
|
|
|