Final | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PASS |
Mark Moncarr
|
|
|
Inspection requested via web by Jennifer Sims Looked at on 2/22/17, homeowners forget to call in for inspection
|
Final | 2/14/2017 | 2/17/2017 | 2/17/2017 | A | FAIL |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Jennifer Sims Need access to outlets for testing. Needs an intersystem bond on garage, utlities are present. Also panel needs labeled.
|
Final | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | NR |
Mark Moncarr
|
|
|
Inspection requested via web by Jennifer Sims Talked to homeowner on 2/15/17, both finals for 16-03774 garage, and 16-03775 for house will be rescheduled for Fri 2/17/17. Also seperate permit needs pulled for spa which was done by an electrical contractor
|
Application received | | | 11/18/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/18/2016 | | DONE |
|
|
|
|