ELE-Aging Inspection | 6/27/2019 | 6/27/2019 | 6/27/2019 | | PASS |
Mark Moncarr
|
|
|
Ok final. Lugs in parking lot light poles were utilized.
|
Final | 6/27/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
Mark Moncarr
|
|
|
Ok final. I had verified that lugs in light poles were utilized.
|
ELE-Aging Inspection | 3/28/2019 | 3/28/2019 | 3/28/2019 | | PASS |
Mark Moncarr
|
|
|
Ok final. Lugs in light poles for GEC were utilized.
|
Electrical Rough-In | 5/10/2017 | 5/11/2017 | 5/11/2017 | A | PASS |
Mark Moncarr
|
|
|
Inspect conduits prior to interior flat work. Phone #: ###-#### Inspection requested via web by Chase Sessions Ok cover ground work
|
Electrical Rough-In | 3/1/2017 | 3/2/2017 | 3/2/2017 | A | PASS |
Eric Story
|
|
|
Inspect conduit runs between light poles for backfil and cover. Phone #: ###-#### Inspection requested via web by Chase Sessions u/g feeding parking lot lights only ok cover
|
Electrical Rough-In | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PASS |
Mark Moncarr
|
|
|
Inspect light pole bases before concrete. Phone #: ###-#### Inspection requested via web by Chase Sessions Ok cover
|
Electrical Rough-In | 12/21/2016 | 12/22/2016 | 12/22/2016 | P | CANC |
Mark Moncarr
|
|
|
Inspect light pole base footings prior to concrete pour. Phone #: ###-#### >> Inspection requested via web by Chase Sessions Inspection cancelled from web by: Chase Sessions
|
Electrical Rough-In | 12/14/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Daryl DeGrange
|
|
|
rough-in ok cover concrete encased electrode
|
Issue PAID IN FULL permit | | | 12/13/2016 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 12/12/2016 | | |
|
|
|
|
Application received | | | 12/12/2016 | | DONE |
|
|
|
This permit was created on the web by Chase Sessions
|
First Notice | 6/27/2019 | 6/27/2019 | | | |
Mark Moncarr
|
|
|
|