Print Statement | | | 3/24/2017 | | DONE |
|
|
|
|
Final | 3/23/2017 | 3/23/2017 | 3/23/2017 | P | PASS |
Tom Saunders
|
|
|
Please make this your last stop of the day if possible. Phone #: ###-#### Inspection requested via web by Sean Patton...
ok to final
|
Electrical Rough-In | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Tom Saunders
|
|
|
Need approval for cover on panel install and ceiling install for workstation circuits to junction boxes. Trying to complete conduit install on lower floor for inspection as well. If you can make this the last inspection of the day we should be good. Phone #: ###-#### Inspection requested via web by Sean Patton...
upstairs ceiling cover and wall cover for new panel....ceiling cover downstairs of 2 inch for feeders to new panel...
|
Fees Due Hold | 3/17/2017 | | 3/17/2017 | | DONE |
|
|
|
|
Conference | 3/7/2017 | 3/8/2017 | 3/8/2017 | A | PASS |
Tom Saunders
|
|
|
I will be onsite at 8 am. Phone #: ###-#### Inspection requested via web by Sean Patton...
discussed adding new sub panel for added workstations....workstation circuits-what needed...permit evaluation of new work added to existing permit
|
Electrical Rough-In | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | PASS |
Tom Saunders
|
|
|
Please call when en route and I will meet you Phone #: ###-#### Inspection requested via web by Sean Patton...
rough ok...most work demo and fished outlets...new circuit breakroom for stove and eddison circuit to add outlets in garage area
|
Issue PAID IN FULL permit | | | 2/14/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/10/2017 | | |
|
|
|
|
Application received | | | 2/10/2017 | | DONE |
|
|
|
This permit was created on the web by Sean Patton
|