First Notice | 6/25/2018 | 6/25/2018 | 11/14/2018 | | DONE |
Eric Story
|
|
|
This permit finaled on the web by Tom Jenkins
|
Final | 6/22/2018 | 6/25/2018 | 6/25/2018 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins Final ok
|
Final | 6/21/2018 | 6/22/2018 | 6/22/2018 | P | CANC |
Eric Story
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tom Jenkins Inspection cancelled from web by: Tom Jenkins
|
Final | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PART |
Eric Story
|
|
|
Part for electrical only ok
|
Electrical Rough-In | 5/24/2018 | 5/24/2018 | 5/24/2018 | P | CANC |
Eric Story
|
|
|
We need a pool light potting inspection please. Thank you. Phone #: ###-#### >> Inspection requested via web by Tom Jenkins Inspection cancelled from web by: Tom Jenkins
|
Electrical Rough-In | 1/18/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Eric Story
|
|
|
ROugh rest of 4th floor rooms and corridor walls and stairwells. Phone #: ###-#### Inspection requested via web by Tom Jenkins Remaining units on 4th floor and corridor walls , stairs also ok to cover
|
Electrical Rough-In | 7/10/2017 | 7/10/2017 | 7/10/2017 | P | PASS |
Eric Story
|
|
|
We need an underground inspection for the West side under floor. Thank you. Dale. Phone #: ###-#### Inspection requested via web by Tom Jenkins West side under ground in slab ok cover
|
Electrical Rough-In | 7/5/2017 | 7/5/2017 | 7/5/2017 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground in floor inspection for the east half of the building. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins Seperate electrical permits required for each buillding permit. Pool, hotel. East 1/2 underfloor underground rough in ok cover
|
Electrical Rough-In | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PASS |
Eric Story
|
|
|
We need a pool bonding inspection. As early as possible Thank you. Dale Phone #: ###-#### Inspection requested via web by Tom Jenkins Pool bonding ok, all four corners and light plus ladder and spa ok cover
|
Electrical Rough-In | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PASS |
Eric Story
|
|
|
We need an underground inspection please. Thank you, Dale. Phone #: ###-#### Inspection requested via web by Tom Jenkins Secondaries and 4" data only ok cover
|
Electrical Rough-In | 6/19/2017 | 6/19/2017 | 6/19/2017 | P | PASS |
Eric Story
|
|
|
Inspection of conduit underground Phone #: ###-#### Inspection requested via web by Tom Jenkins U/G for temp power and light in garbage area ok cover
|
Electrical Rough-In | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | PASS |
Eric Story
|
|
|
We need an underground inspection please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g south next to building ok cover-3/4@2 inch conduits run along side outside wall.
|
Electrical Rough-In | 6/5/2017 | 6/6/2017 | 6/6/2017 | A | PASS |
Eric Story
|
|
|
Ufer Phone #: ###-#### Inspection requested via web by Tom Jenkins Concrete electrode ok to cover
|
Electrical Rough-In | 6/2/2017 | 6/2/2017 | 6/2/2017 | A | PASS |
Eric Story
|
|
|
Underground for feeders by building. Phone #: ###-#### Inspection requested via web by Tom Jenkins 8-5" conduits and LV conduit to stem wall ok cover
|
Electrical Rough-In | 6/1/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Eric Story
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Tom Jenkins Secondary conduits to building ok cover
|
Electrical Rough-In | 5/25/2017 | 5/26/2017 | 5/26/2017 | A | NR |
Daryl DeGrange
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Tom Jenkins Buried conduit running north and south near job trailer for parking lot lighting covered without inspection, requires test hole. Future covers with no inspections will requires entire run exposed. Not ready for cover
|
Electrical Rough-In | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Eric Story
|
|
|
We need a light pole base inspection please. Thank you, Dale Phone #: ###-#### Inspection requested via web by Tom Jenkins Light pole bases grounding ok, ok to pour
|
Electrical Rough-In | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Eric Story
|
|
|
We need an underground inspection please. Thank you. Dale Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g north on elder ok cover
|
Electrical Rough-In | 5/11/2017 | 5/12/2017 | 5/12/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g on east side and west side site work ok cover
|
Electrical Rough-In | 5/8/2017 | 5/9/2017 | 5/9/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g for parking lot lights as marked on prints ok cover
|
Issue PAID IN FULL permit | | | 5/8/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/8/2017 | | DONE |
|
|
|
This permit was created on the web by Tom Jenkins
|