Final | 10/22/2018 | 10/24/2018 | 10/24/2018 | A | PASS |
Mark Moncarr
|
|
|
James Phone #: ###-#### Ok final.
|
Final | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | NR |
Mark Moncarr
|
|
|
James Phone #: ###-#### 100a breaker installed in a 100a meter main to feed a shop. Asked homeowner to produce a load calculation for house and shop. Will probably need to be replaced with 60a brkr to feed shop.
|
Final | 1/29/2018 | 1/31/2018 | 1/31/2018 | A | CANC |
Mark Moncarr
|
|
|
Please call ahead for access - James Phone #: ###-#### I changed inspection to a RI.
|
Electrical Rough-In | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PASS |
Mark Moncarr
|
|
|
Ok cover shop.
|
Conference | 8/23/2017 | 8/23/2017 | 8/23/2017 | A | DONE |
Mark Moncarr
|
|
|
Please call ahead for access - James Phone #: ###-#### Discussed ground screws for metal boxes. GFI's need to be readily accesibile. 12/3 romex needs pulled out of conduit with feeders feeding garage panel. Some type of permanent platform may need built for service change.
|
Electrical Rough-In | 8/21/2017 | 8/23/2017 | 8/23/2017 | A | CANC |
Mark Moncarr
|
|
|
Please call ahead for access - James Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/11/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/11/2017 | | DONE |
|
|
|
This permit was created on the web by James McColly
|