Final | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
James Ady
|
|
|
The only receptacle changed in the kitchen was the refer receptacle. Home owner will be there. Phone #: ###-#### Inspection requested via web by Anastacio Fuentes Final ok
|
Electrical Rough-In | 7/25/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
James Ady
|
|
|
The changing of receptacles and switches are complete. Basement rough for lighting so they can cover. Any questions call JR at ###-#### Phone #: ###-#### Inspection requested via web by Anastacio Fuentes Checked replace receps in upstairs only OK Rough in down stairs ceiling only ok to cover
|
Issue PAID IN FULL permit | | | 7/25/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/25/2017 | | DONE |
|
|
|
This permit was created on the web by Anastacio Fuentes
|