Final | 9/12/2017 | 9/12/2017 | 9/12/2017 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald...
corrections made...ok to final
|
Final | 9/11/2017 | 9/12/2017 | 9/12/2017 | A | FAIL |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald...
1) screws rated for box need installed on switches in bathroom
2) box extension needs installed on box in bathrrom...box recessed more than 1/4 inch
3) service outlet for rooftop units shows hot/grnd reversed
|
Electrical Rough-In | 8/30/2017 | 8/30/2017 | 8/30/2017 | P | PASS |
Tom Saunders
|
|
|
Pole base inspection Phone #: ###-#### Inspection requested via web by Ben Archibald..
ok to pour
|
Rough-In Permanent Service | 8/2/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Tom Saunders
|
|
|
The ceiling need inspected as well Phone #: ###-#### Inspection requested via web by Ben Archibald...
ceiling ok to cover p/s u/g n ok
|
Electrical Rough-In | 7/27/2017 | 7/28/2017 | 7/28/2017 | A | PASS |
Rock A. Hudson
|
|
|
Under ground and wall inspection Phone #: ###-#### Inspection requested via web by Ben Archibald Underground to be 30"+ once back fill is in. Underground and walls rough in ok cover
|
Issue PAID IN FULL permit | | | 7/27/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 7/27/2017 | | |
|
|
|
|
Application received | | | 7/27/2017 | | DONE |
|
|
|
This permit was created on the web by Ben Archibald
|
First Notice | 9/12/2017 | 9/12/2017 | | | |
Tom Saunders
|
|
|
|