Final | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Mark Moncarr
|
|
|
left a ladder for access to the rough. Let me know if you have questions. All panels are U.L. Listed. Inverters are Enphase M-250. 4- solar panels 275 watt and 4 inverters. Phone #: ###-#### Inspection requested via web by daniel bibikov Ok final
|
Electrical Rough-In | 8/21/2017 | 8/21/2017 | 8/21/2017 | P | PASS |
Mark Moncarr
|
|
|
left a ladder for access to the rough. Let me know if you have questions. All panels are U.L. Listed. Inverters are Enphase M-250. 4- solar panels 275 watt and 4 inverters. Phone #: ###-#### Inspection requested via web by daniel bibikov
|
Issue PAID IN FULL permit | | | 8/21/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/21/2017 | | DONE |
|
|
|
This permit was created on the web by daniel bibikov
|