First Notice | 9/21/2017 | 9/21/2017 | 9/5/2019 | | DONE |
Tom Saunders
|
|
|
This permit finaled on the web by Steve McCloy
|
Final | 9/20/2017 | 9/21/2017 | 9/21/2017 | A | PASS |
Tom Saunders
|
|
|
Call Gil, the General Contractor for Falash ; Ross if you have any questions. Phone #: ###-#### Inspection requested via web by Steve McCloy...
ok to final
|
Electrical Rough-In | 8/28/2017 | 8/29/2017 | 8/29/2017 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Steve McCloy....
rough ok to cover outlet in new wall and relocated switch for light
|
Issue PAID IN FULL permit | | | 8/28/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/28/2017 | | DONE |
|
|
|
This permit was created on the web by Steve McCloy
|