Final | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Tom Saunders
|
|
|
Meter cab - final Phone #: ###-#### Inspection requested via web by steve ragan...ok to final
|
Permanent Service | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Tom Saunders
|
|
|
Meter cab service inspection Phone #: ###-#### Inspection requested via web by steve ragan...
p/s u/g new ok
|
Electrical Rough-In | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PASS |
Tom Saunders
|
|
|
Underground Inspection Phone #: ###-#### Inspection requested via web by steve ragan...
ok to cover
|
Issue PAID IN FULL permit | | | 9/14/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/14/2017 | | DONE |
|
|
|
This permit was created on the web by steve ragan
|
First Notice | 11/7/2017 | 11/7/2017 | | | |
Tom Saunders
|
|
|
|