Final | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Mark Moncarr
|
|
|
Will meet you there Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok final.
|
Electrical Rough-In | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Mark Moncarr
|
|
|
We will be onsite Phone #: ###-#### Inspection requested via web by Jesse Simpson RI inspection was already done in Oct. 2017. This was supposed to be a final. A final was called in for 1/12/18
|
Electrical Rough-In | 10/11/2017 | 10/11/2017 | 10/11/2017 | P | PASS |
Mark Moncarr
|
|
|
the customer will be home today and the earlier we can get to the inspection the better. I will bring a panel and optimizer to show UL listings. Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok cover. All items UL listed.
|
Application received | | | 10/3/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/3/2017 | | DONE |
|
|
|
|