Final | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PASS |
Mark Moncarr
|
|
|
Contact: Jason Noble Phone #: ###-#### Inspection requested via web by Deb Gooden Ok final. Grounds/neutrals seperated in existing panel. Bonding in new service at alley way. Guy kit will be onsite. A new roof is being put on, guy kit will be installed after.
|
Permanent Service | 10/26/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Mark Moncarr
|
|
|
Contact: Jason Noble Phone #: ###-#### Inspection requested via web by Deb Gooden p/s o/h n ok. Talked to troubleman on site. They wanted approval to energize service so long as the contractor safes off main breaker in all in one on detached garage until house panel is completed.
|
Conference | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | DONE |
Mark Moncarr
|
|
|
Contact: Jason Noble.... early morning consult if possible please Phone #: ###-#### Inspection requested via web by Deb Gooden Discussed re-location of service to detached garage and re-feed house panel.
|
Issue PAID IN FULL permit | | | 10/24/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/24/2017 | | DONE |
|
|
|
This permit was created on the web by Deb Gooden
|