Print Statement | | | 11/16/2018 | | DONE |
|
|
|
|
Final | 5/4/2018 | 5/7/2018 | 5/7/2018 | A | PASS |
Tom Saunders
|
|
|
first thing monday...rescheduled from friday...call Bryan A & B...job complete...ok to final
|
Final | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...rescheduled to Monday 7th
|
Final | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | PART |
Tom Saunders
|
|
|
Partial Final Owner Moving Equipment from Previous Building Phone #: ###-#### Inspection requested via web by Bryan Atkins...dwn stairs and upstairs offices ok...temp so can start moving in...warehouse left to look at-waiting for equipment to hookup, A/C x 2, bonding LV racks, check panel labels
|
Electrical Rough-In | 3/27/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Tom Saunders
|
|
|
First Floor Ceiling Phone #: ###-#### Inspection requested via web by Bryan Atkins....ceiling ok to cover...discussed grounding of parking lot lights
|
Electrical Rough-In | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Tom Saunders
|
|
|
Ceiling inspection second floor Phone #: ###-#### Inspection requested via web by Bryan Atkins...grid ok to cover
|
Permanent Service | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...p/s u/g new ok
|
Electrical Rough-In | 2/9/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Tom Saunders
|
|
|
ok to bat insulate inbetween 1st and 2nd floor...drop ceiling inspection will be scheduled at later date
|
Electrical Rough-In | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Tom Saunders
|
|
|
Rough-in walls 1st floor. Phone #: ###-#### Inspection requested via web by Bryan Atkins...first floor walls ok to cover
|
Electrical Rough-In | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | PASS |
Eric Story
|
|
|
Rough-in walls second floor Phone #: ###-#### Inspection requested via web by Bryan Atkins Upstairs only walls ok to cover
|
Electrical Rough-In | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | NR |
Eric Story
|
|
|
Rough-in walls Phone #: ###-#### Inspection requested via web by Bryan Atkins 1st floor not ready
|
Electrical Rough-In | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Tom Saunders
|
|
|
underground Phone #: ###-#### Inspection requested via web by Bryan Atkins...laterals from transformer...ok to cover
|
Electrical Rough-In | 11/6/2017 | 11/6/2017 | 11/6/2017 | P | PASS |
Tom Saunders
|
|
|
Underground R/I Phone #: ###-#### Inspection requested via web by Bryan Atkins...ok to cover
|
Electrical Rough-In | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | PASS |
Eric Story
|
|
|
Ufer and underground Phone #: ###-#### Inspection requested via web by Bryan Atkins Concrete encased electrode and u/g thru middle form and secondaries ok to cover
|
Issue PAID IN FULL permit | | | 10/25/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/25/2017 | | DONE |
|
|
|
This permit was created on the web by Bryan Atkins
|
First Notice | 5/7/2018 | 5/7/2018 | | | |
Tom Saunders
|
|
|
|