First Notice | 2/21/2018 | 2/21/2018 | 7/24/2019 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Kurt Carlson
|
Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | PASS |
Rock A. Hudson
|
|
|
Requesting Final Inspection for 1st floor. Randy Fox will be on site to assist , if needed. Phone #: ###-#### Inspection requested via web by Kurt Carlson Final ok
|
Final | 1/25/2018 | 1/25/2018 | 1/25/2018 | A | FAIL |
Rock A. Hudson
|
|
|
Large office areas on the east and west ends (north side) are ready for final inspection. Randy Fox will be on site. Call with any questions ###-#### Kurt Carlson Phone #: ###-#### Inspection requested via web by Kurt Carlson 210.8- Receptacle located in vanilla space shall have GFCI protection for construction. 300.15- Several wires in misc rooms, bathroom open and wiring not terminated in a boxes in baths. Dishwashers in break rooms not terminated. Walked all office and few receptacle covers missing and 2 gang junction boxes open. Non electrical furniture in place unable to check all receptacles. Will recall when ready.
|
Electrical Rough-In | 1/8/2018 | 1/8/2018 | 1/8/2018 | A | PASS |
Rock A. Hudson
|
|
|
Requesting a ceiling overhead rough in , Northwest end of building. all seismic wires to boxes and lights are installed. I will be on site. Thanks Kurt Phone #: ###-#### Inspection requested via web by Kurt Carlson Area noted grid rough in ok cover
|
Electrical Rough-In | 1/3/2018 | 1/3/2018 | 1/3/2018 | P | PASS |
Rock A. Hudson
|
|
|
Requesting a overhead ceiling rough in, for East end area. Lighting seismic wires for all fixtures are installed, existing raceways have been strapped and supported, new equipment installed. Phone #: ###-#### Inspection requested via web by Kurt Carlson Area noted east grid rough in ok cover
|
Electrical Rough-In | 12/27/2017 | 12/27/2017 | 12/27/2017 | P | PASS |
Rock A. Hudson
|
|
|
As per (316) structural inspector drywall accounts for 2.3 lbs per sq. in. of a 10 lbs per sq. in. rated ceiling system so the amount of MC cables on grid not a concern. As per 316 and 445 hard lid rough in ok cover. As noted on contractor print.
|
Electrical Rough-In | 12/25/2017 | 12/26/2017 | 12/26/2017 | A | FAIL |
Rock A. Hudson
|
|
|
Requesting a ceiling / rough in inspection for the main corridor, new corridore will be hard rock lid. I will be on site, to show area for inspection. Phone #: ###-#### Inspection requested via web by Kurt Carlson 300.11- Suspended ceiling system shall not be used to support cables unless manufacturers instructions state ceiling system rated for support.
|
Electrical Rough-In | 12/20/2017 | 12/20/2017 | 12/20/2017 | A | PASS |
Daryl DeGrange
|
|
|
I will meet you on site, need specific area walls and ceiling inspected. thanks Kurt Phone #: ###-#### Inspection requested via web by Kurt Carlson Rough-in ok cover walls as marked and dated on plans
|
Electrical Rough-In | 11/22/2017 | 11/22/2017 | 11/22/2017 | A | PASS |
Daryl DeGrange
|
|
|
Requesting partial inspection of walls. I will be on site to show areas requested. Thnak''s Kurt Carlson Phone #: ###-#### Inspection requested via web by Kurt Carlson Rough-in ok cover walls marked and dated on plans
|
Electrical Rough-In | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Rock A. Hudson
|
|
|
Requesting a partial rough in inspection, located on the east end of the building. I will meet on site, we will have a check off plan available for the inspector to show inspection locations. Thanks Kurt Phone #: ###-#### Inspection requested via web by Kurt Carlson As noted on contractor print wall rough in east of lobby rough in ok cover.
|
Issue PAID IN FULL permit | | | 11/14/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 11/14/2017 | | |
|
|
|
|
Application received | | | 11/14/2017 | | DONE |
|
|
|
This permit was created on the web by Kurt Carlson
|