Print Statement | | | 5/17/2018 | | DONE |
|
|
|
|
Final | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PASS |
Tom Saunders
|
|
|
Final electrical inspection please Phone #: ###-#### Inspection requested via web by Kyle Lott..job complete...ok to final
|
Final | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PART |
Mark Moncarr
|
|
|
Final please Phone #: ###-#### Inspection requested via web by Kyle Lott Partial final. Reader board needs to be set in place. All other corrections made. Electrician is going to make new panel schedules upon final.
|
Final | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | FAIL |
Tom Saunders
|
|
|
Final inspection please. Phone #: ###-#### Inspection requested via web by Kyle Lott...
1) outside GFI needs outdoor rated 2) open junction box in ceiling above panels 3) double GFI protection on kitchen circuits 4) GFIs need to be readily accessible 5) finishe exterior reader/order/menu boards
|
Final | 2/11/2018 | 2/12/2018 | 2/12/2018 | P | NR |
Tom Saunders
|
|
|
Final please. Have a bless week! Phone #: ###-#### Inspection requested via web by Kyle Lott...requested by mistake...need ceiling cover..checked some GFI protection while there
|
Electrical Rough-In | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Tom Saunders
|
|
|
Final please. Have a bless week! Phone #: ###-#### Inspection requested via web by Kyle Lott...full ceiling ok to cover
|
Electrical Rough-In | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PASS |
Tom Saunders
|
|
|
Partial ceiling inspection please. Also, contractor is requesting to do border where ceiling grid is installed. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...ok to cover grid area excluding panel area and back room
|
Conference | 1/18/2018 | 1/18/2018 | 1/18/2018 | P | DONE |
Rock A. Hudson
|
|
|
Discussed with general foreman what needed for temp occupancy so store could be stocked. Informed general foreman and electrical wireman on site will not grant TCO with out electrical contractors request and areas wanting to stock must be called in and checked prior to stocking with materials. Inspector shall have access to all electrical boxes, equipment, and connections prior to stocking.
|
Electrical Rough-In | 12/20/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Tom Saunders
|
|
|
Rough in please. Have a bless Christmas!!! Phone #: ###-#### Inspection requested via web by Kyle Lott...exterior walls drive thru area, bathrooms, back employee area, other areas discussed with contractor
|
Electrical Rough-In | 11/29/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Tom Saunders
|
|
|
Underground inspection please. Phone #: ###-#### Inspection requested via web by Kyle Lott...TI underground, floor boxes and feeds..ok to cover
|
Issue PAID IN FULL permit | | | 11/18/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 11/18/2017 | | |
|
|
|
|
Application received | | | 11/18/2017 | | DONE |
|
|
|
This permit was created on the web by Kyle Lott
|
First Notice | 3/7/2018 | 3/7/2018 | | | |
Tom Saunders
|
|
|
|