Final | 1/30/2018 | 1/31/2018 | 1/31/2018 | P | PASS |
James Ady
|
|
|
Approved plans onsite. The homeowner can be reached at ###-#### to coordinate access, someone should be onsite all afternoon. Phone #: ###-#### Inspection requested via web by Ryan King final ok
|
Electrical Rough-In | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PASS |
James Ady
|
|
|
Approved plans onsite. The homeowner can be reached at ###-#### to coordinate access, someone should be onsite all afternoon. Phone #: ###-#### Inspection requested via web by Ryan King met contractor onsite with panels and optimizers. UL ok
|
Issue PAID IN FULL permit | | | 11/28/2017 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/28/2017 | | DONE |
|
|
|
This permit was created on the web by Ryan King
|