First Notice | 1/16/2018 | 1/16/2018 | 5/30/2018 | | DONE |
Eric Story
|
|
|
This permit finaled on the web by Chris Berthelot
|
Final | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Berthelot Final ok
|
Final | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | CANC |
Eric Story
|
|
|
move micro outlet and reinstall d/w outlet Phone #: ###-#### Inspection requested via web by Chris Berthelot Needed rough-in
|
Electrical Rough-In | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Eric Story
|
|
|
move micro outlet and reinstall d/w outlet Phone #: ###-#### Inspection requested via web by Chris Berthelot Breakroom d/w and micro wall only ok to cover, Did not have a sticker on hand due to it was called in as final..
|
Issue PAID IN FULL permit | | | 1/4/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/4/2018 | | DONE |
|
|
|
This permit was created on the web by Chris Berthelot
|