Final | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Mark Moncarr
|
|
|
Dan ###-#### Inspection requested via web by Dan Hobdey Ok final.
|
Electrical Rough-In | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Mark Moncarr
|
|
|
Adu unit ok to cover Dan ###-#### Inspection requested via web by Dan Hobdey Ok cover. See conference notes.
|
Conference | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | DONE |
Mark Moncarr
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Dan Hobdey Discussed feeding a 100a panel inside existing garage that is changing to an ADU. 200a meter main is installed on garage which is a different address than the house. The property is on one parcel and cannot be divided up.
|
Issue PAID IN FULL permit | | | 1/9/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/9/2018 | | DONE |
|
|
|
This permit was created on the web by Dan Hobdey
|