Final | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Mark Moncarr
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Ok final. Required labels present. Disc set beside meter on N side of house.
|
Electrical Rough-In | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Mark Moncarr
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Ok cover. All items UL listed. Contractors are waiting on shipment of panels. Talked to George, panels are the same panels they have been using.
|
Issue PAID IN FULL permit | | | 1/9/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/9/2018 | | DONE |
|
|
|
This permit was created on the web by Christian Kilpatrick
|