Final | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Tom Saunders
|
|
|
Final please Phone #: ###-#### Inspection requested via web by Kyle Lott...complete...ok to final
|
Final | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Tom Saunders
|
|
|
Final inspection please. Have a bless week! Phone #: ###-#### Inspection requested via web by Kyle Lott...partial final...waiting on Gelato case to be wired and breaker lockouts for hardwired ovens x 2
|
Electrical Rough-In | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Tom Saunders
|
|
|
Ceiling inspection please. Have a bless weekend! Phone #: ###-#### Inspection requested via web by Kyle Lott...drop ceiling grid ok to cover...kit x 3 and back panel room
|
Electrical Rough-In | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Tom Saunders
|
|
|
Bathroom electrical rough in please. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...ceiling ok to cover
|
Electrical Rough-In | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | PASS |
Tom Saunders
|
|
|
Hard lid ceiling inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...hard lids minus bathrooms ok to cover
|
Electrical Rough-In | 3/6/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Tom Saunders
|
|
|
Rough in walls only inspection. Hard lid ceiling not complete. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...wall cover ok
|
Permanent Service | 2/7/2018 | 2/8/2018 | 2/8/2018 | A | CANC |
Tom Saunders
|
|
|
We need underground inspection please. I chose permanent service inspection type, since there is no underground inspection option. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...needed rough underground
|
Electrical Rough-In | 2/8/2018 | 2/8/2018 | 2/8/2018 | A | PASS |
Tom Saunders
|
|
|
We need underground inspection please. I chose permanent service inspection type, since there is no underground inspection option. Thank you. Phone #: ###-#### Inspection requested via web by Kyle Lott...underground feeds ok to cover
|
Issue PAID IN FULL permit | | | 1/12/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/12/2018 | | DONE |
|
|
|
This permit was created on the web by Kyle Lott
|
First Notice | 6/21/2018 | 6/21/2018 | | | |
Tom Saunders
|
|
|
|