First Notice | 2/22/2018 | 2/22/2018 | 3/20/2018 | | DONE |
Eric Story
|
|
|
This permit finaled on the web by Samatha Solberg
|
Final | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Eric Story
|
|
|
Check GFCI for fountain and front counter top outlets in-op Final ok Card signed
|
Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | P | PART |
Eric Story
|
|
|
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg Partial ok
|
Electrical Rough-In | 2/1/2018 | 2/2/2018 | 2/2/2018 | P | PASS |
Tom Saunders
|
|
|
David Joseph ###-#### Cover inspection Phone #: ###-#### Inspection requested via web by Samatha Solberg...grid ok to cover..verify outlets not being used above grid ceiling at final
|
Electrical Rough-In | 1/16/2018 | 1/17/2018 | 1/17/2018 | A | PASS |
Tom Saunders
|
|
|
Justin ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg...walls ok to cover...new switching only
|
Issue PAID IN FULL permit | | | 1/16/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/16/2018 | | DONE |
|
|
|
This permit was created on the web by Samatha Solberg
|