First Notice | 8/23/2018 | 8/23/2018 | 11/14/2018 | | DONE |
Candy A. Nichols
|
|
|
This permit finaled on the web by Tom Jenkins
|
Final | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Tom Saunders
|
|
|
We would like a final inspection for this project. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins...job complete...ok to final
|
Final | 8/16/2018 | 8/17/2018 | 8/17/2018 | P | PART |
Tom Saunders
|
|
|
We need a final inspection for this building please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins...
partial final temp occ ok breaker L/O needed on water htr and dishwasher bonding to LV cabinet needs done breaker for reader board #37 not holding roof top units labelled and verified..access to roof
|
Electrical Rough-In | 8/9/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Tom Saunders
|
|
|
We need a ceiling cover inspection for the drive thru area please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins... canopy drive thru ok to cover...all junction boxes be accessible thru springed tiles
|
Electrical Rough-In | 7/20/2018 | 7/20/2018 | 7/20/2018 | A | PASS |
Rock A. Hudson
|
|
|
We need a ceiling cover inspection for acoustical grid areas please. Thank you, Dale. Phone #: ###-#### Inspection requested via web by Tom Jenkins Grid rough in ok cover
|
Permanent Service | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...p/s u/g new ok
|
Electrical Rough-In | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...piping and fixture whip for sky light lighting above framing ok to cover
|
Electrical Rough-In | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover ceiling in vault, main entrance ceiling S side, and ceiling W side entrance.
|
Electrical Rough-In | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...hard lids mech rm and atm rm...misc wall cover ok
|
Electrical Rough-In | 6/1/2018 | 6/4/2018 | 6/4/2018 | A | PASS |
Tom Saunders
|
|
|
Interior walls Phone #: ###-#### Inspection requested via web by Tom Jenkins...east/west window walls ok to cover
|
Electrical Rough-In | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Tom Saunders
|
|
|
Rough in of back of house interior walls Phone #: ###-#### Inspection requested via web by Tom Jenkins...verified ground screws in all boxes...all walls ok to cover at this time
|
Electrical Rough-In | 5/29/2018 | 5/30/2018 | 5/29/2018 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins....ok to cover...exterior walls only
|
Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...soffitts for exterior cans...wiring method ok
|
Electrical Rough-In | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Mark Moncarr
|
|
|
Rough in walls exterior and demising. Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover all walls. Another inspection needed to veruify all boxes have ground pigtails.
|
Electrical Rough-In | 3/4/2018 | 3/5/2018 | 3/5/2018 | A | PASS |
Tom Saunders
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Tom Jenkins...south end pipes and pipe for pole lights..ok to cover
|
Electrical Rough-In | 2/28/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Mark Moncarr
|
|
|
underground Phone #: ###-#### Inspection requested via web by Tom Jenkins Ok cover conduit from transformer to building.
|
Electrical Rough-In | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PASS |
Tom Saunders
|
|
|
Underground for drive through Phone #: ###-#### Inspection requested via web by Tom Jenkins...ok to cover
|
Electrical Rough-In | 2/22/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins...ok to cover
|
Electrical Rough-In | 2/21/2018 | 2/23/2018 | 2/22/2018 | A | CANC |
Tom Saunders
|
|
|
Rest of Pad Phone #: ###-#### >> Inspection requested via web by Tom Jenkins Inspection cancelled from web by: Tom Jenkins
|
Electrical Rough-In | 2/20/2018 | 2/20/2018 | 2/20/2018 | A | PASS |
Tom Saunders
|
|
|
underground pad Phone #: ###-#### Inspection requested via web by Tom Jenkins...ok to cover...south end at this time
|
Electrical Rough-In | 1/31/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Tom Saunders
|
|
|
Ufer Ground Phone #: ###-#### Inspection requested via web by Tom Jenkins...bare copper ok to cover
|
Issue PAID IN FULL permit | | | 1/31/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/31/2018 | | DONE |
|
|
|
This permit was created on the web by Tom Jenkins
|