First Notice | 5/23/2018 | 5/23/2018 | 6/27/2018 | | DONE |
Tom Saunders
|
|
|
This permit finaled on the web by Stacie Tasker
|
Final | 5/22/2018 | 5/23/2018 | 5/23/2018 | P | PASS |
Tom Saunders
|
|
|
Dustin is the site contact. Thank you. Phone #: ###-#### Inspection requested via web by Stacie Tasker...job complete...ok to final
|
Electrical Rough-In | 5/23/2018 | 5/23/2018 | 5/23/2018 | P | PASS |
Tom Saunders
|
|
|
Dustin is the site contact. Thank you. Phone #: ###-#### Inspection requested via web by Stacie Tasker...grid ceiling complete...ok to cover
|
Electrical Rough-In | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | PASS |
Tom Saunders
|
|
|
We need a ceiling inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...open junction boxes from previous inspection verified made up from access in hallway...grid cover ok on listed rooms with contractor
|
Electrical Rough-In | 5/10/2018 | 5/11/2018 | 5/11/2018 | P | PART |
James Ady
|
|
|
We need a ceiling inspection. Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Borders had already been installed. Found 2 burried J boxes behind tiles. Asked that border tile be removed and boxes made up and inspected. Areas ok to cover listed on electricians Note pad.
|
Permanent Service | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Tom Saunders
|
|
|
contact is Dustin ###-####...p/s u/g new ok
|
Permanent Service | 5/2/2018 | 5/2/2018 | 5/2/2018 | P | NR |
Tom Saunders
|
|
|
Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...not ready...rescheduled to next day
|
Electrical Rough-In | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Rock A. Hudson
|
|
|
We need a wall cover inspection, thank you. Dustin is your on-site contact and can be reached at 208.293.4442. Phone #: ###-#### Inspection requested via web by Stacie Tasker Underground not metallic. Reception area 1/2 walls non patient care rough in ok cover
|
Electrical Rough-In | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Tom Saunders
|
|
|
We need a wall cover. Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...wall cover ok as marked on plans
|
Electrical Rough-In | 3/30/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Travis will be the contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Interior still shut down due to mold issue. Service entrance conduits on rear of building rough in ok cover.
|
Electrical Rough-In | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | FAIL |
Tom Saunders
|
|
|
We need a wall cover inspection. Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...no access...reported black mold in work area ceiling...treatment of black mold has been performed...proper safety equipment shall be supplied and required to enter site and do inspection
|
Electrical Rough-In | 3/16/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Tom Saunders
|
|
|
We need a wall cover inspection. Dustin is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker...wall cover ok dated and marked on plans
|
Electrical Rough-In | 3/14/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Tom Saunders
|
|
|
We need a wall cover inspection, Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker..wall ok to cover as marked on plans
|
Electrical Rough-In | 3/9/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Tom Saunders
|
|
|
We need a partial wall cover. Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...walls ok to cover...rms as marked on plans
|
Issue PAID IN FULL permit | | | 2/1/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/1/2018 | | DONE |
|
|
|
This permit was created on the web by Stacie Tasker
|