Final | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Mark Moncarr
|
|
|
Per Dave H Ok final. I talked to Perry the electrician. There was a condensate pump installed for new furnace in ceiling. Right now there is an extension cord being used for power for this pump. I scheduled an inspection for 8/16/18 to touch base with Perry. Power is going to be supplied for this pump via junction box.
|
Electrical Rough-In | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Mark Moncarr
|
|
|
Grid cover Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover. Ceiling tile was installed prior to inspection. A ladder was on site. Was able to look above tile in a few areas.
|
Electrical Rough-In | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Mark Moncarr
|
|
|
Wall rough in inspect Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover offices in NW corner of building.
|
Issue PAID IN FULL permit | | | 2/14/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/14/2018 | | |
|
|
|
|
Application received | | | 2/14/2018 | | DONE |
|
|
|
This permit was created on the web by Stephanie Huston
|