Final | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
James Ady
|
|
|
Approved plans onsite. Please call homeowner ahead of time to gain access, ###-####. Ryan King can answer questions, ###-####. Phone #: ###-#### Inspection requested via web by Ryan King Final ok
|
Final | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | NH |
Rock A. Hudson
|
|
|
Approved plans onsite. Please call homeowner ahead of time to gain access, ###-####. Ryan King can answer questions, ###-####. Phone #: ###-#### Inspection requested via web by Ryan King Called contact as instructed for access provided 1/2 hr for return phone call. Called contractor left message to reschedule.
|
Electrical Rough-In | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
James Ady
|
|
|
Listing inspection for optimizers and panels. Rooftop installation crew will be onsite. Phone #: ###-#### Inspection requested via web by Ryan King listing only ok
|
Issue PAID IN FULL permit | | | 2/21/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/21/2018 | | DONE |
|
|
|
This permit was created on the web by Ryan King
|