Final | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Buster Bowen Underground only Final ok
|
Electrical Rough-In | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
James Ady
|
|
|
UG for planter in area B. Danny is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen UG in planter walls ok to cover
|
Electrical Rough-In | 8/31/2018 | 8/31/2018 | 8/31/2018 | P | PASS |
Rock A. Hudson
|
|
|
UG cover. Danny is onsite Phone #: ###-#### Inspection requested via web by Buster Bowen Underground on eastside along back to center of complex rough in ok cover
|
Electrical Rough-In | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | PASS |
James Ady
|
|
|
Site UG Cover. Danny is onsite. Phone #: ###-#### Inspection requested via web by Buster Bowen UG ok to cover
|
Electrical Rough-In | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | PASS |
James Ady
|
|
|
UG cover. Danny is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen Underground from Com conduits and 3/4 stubs out of electrical room only ok
|
Electrical Rough-In | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
James Ady
|
|
|
UG cover. Danny is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen Underground for temp power at trailers and middle of project only ok to cover
|
Electrical Rough-In | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | NH |
Rock A. Hudson
|
|
|
UG Cover. Danny is the onsite contact. Phone #: ###-#### Inspection requested via web by Buster Bowen Called contact, no answer, left message to recall when someone is available to meet on area to inspect.
|
Electrical Rough-In | 4/4/2018 | 4/5/2018 | 4/5/2018 | A | PASS |
James Ady
|
|
|
UG cover Phone #: ###-#### Inspection requested via web by Buster Bowen UG Along south wall only
|
Electrical Rough-In | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PASS |
James Ady
|
|
|
UG cover. Phone #: ###-#### Inspection requested via web by Buster Bowen underground ok to cover
|
Electrical Rough-In | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | PASS |
James Ady
|
|
|
UG Cover. Danny is the onsite contact. Phone #: ###-#### Inspection requested via web by Buster Bowen Underground duct bank running NE to SW middle of building ok to cover
|
Electrical Rough-In | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Rock A. Hudson
|
|
|
UG Cover. Danny is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen North portion of service entrance conduits, Generator conduits and Data underslab rough in ok cover
|
Electrical Rough-In | 3/7/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
James Ady
|
|
|
Ufer Ground. Danny is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen ufer only ok
|
Issue PAID IN FULL permit | | | 3/7/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/7/2018 | | DONE |
|
|
|
This permit was created on the web by Sean DeLacy
|
First Notice | 11/8/2018 | 11/8/2018 | | | |
James Ady
|
|
|
|