Final | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Eric Story
|
|
|
Inspection for final of entire space. Please call Tyler (###-####) with questions. Phone #: ###-#### Inspection requested via web by Scott Campbell Card not onsite final ok
|
Final | 8/20/2018 | 8/21/2018 | 8/21/2018 | A | PART |
Eric Story
|
|
|
Card not on site Temp occ ok for main area only
|
Final | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | CANC |
Eric Story
|
|
|
Requesting partial final to achieve occupancy on (3) large rooms in West of T.I. Please call Tyler (###-####) for specifics. Phone #: ###-#### Inspection requested via web by Scott Campbell not ready
|
Change Status to I | | | 8/20/2018 | | DONE |
|
|
|
per Eric Story, reopen permit, didnt mean to final yet
|
Electrical Rough-In | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Eric Story
|
|
|
Inspect ceiling for cover. Call Tyler Reed (###-####) for specifics. Phone #: ###-#### Inspection requested via web by Scott Campbell Suspended ceiling in main and window wall ok to cover
|
Electrical Rough-In | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Tom Saunders
|
|
|
Inspection for ceiling cover. Please call Tyler Reed (###-####) with any questions. Phone #: ###-#### Inspection requested via web by Scott Campbell....construction entry/hall only...open rooms to left and back need cleaned up-whips on grid, whips over 6', whips needing supports
|
Electrical Rough-In | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Eric Story
|
|
|
Please call Tyler (###-####) for specifics. Phone #: ###-#### Inspection requested via web by Scott Campbell u/g ok to cover
|
Electrical Rough-In | 4/6/2018 | 4/10/2018 | 4/10/2018 | A | PASS |
Eric Story
|
|
|
Inspection for rough-in cover. Phone #: ###-#### Inspection requested via web by Scott Campbell Walls only and u/g for floor boxes only ok to cover
|
Issue PAID IN FULL permit | | | 3/12/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/12/2018 | | DONE |
|
|
|
This permit was created on the web by Scott Campbell
|