Final | 4/5/2018 | 4/5/2018 | 4/5/2018 | P | PASS |
James Ady
|
|
|
Steve Phone #: ###-#### Final ok
|
Final | 3/16/2018 | 3/19/2018 | 3/19/2018 | P | NR |
James Ady
|
|
|
For underground and service. Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek not ready for final
|
Rough-In Permanent Service | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
James Ady
|
|
|
For underground and service. Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek underground from transformer to main service ok to cover. p/s u/g rec ok
|
Issue PAID IN FULL permit | | | 3/12/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/12/2018 | | DONE |
|
|
|
This permit was created on the web by Cathy Duchek
|
First Notice | 4/5/2018 | 4/5/2018 | | | |
James Ady
|
|
|
|