Final | 10/29/2018 | 10/31/2018 | 10/30/2018 | A | PASS |
Tom Saunders
|
|
|
Please call Max Phone #: ###-#### Inspection requested via web by Kevin Perez... job complete...ok to final
|
Final | 10/30/2018 | 10/31/2018 | 10/30/2018 | P | CANC |
Tom Saunders
|
|
|
Please Call Max Cole Phone #: ###-#### >> Inspection requested via web by Kevin Perez Inspection cancelled from web by: Kevin Perez
|
Final | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | NR |
Tom Saunders
|
|
|
Please call Max Phone #: ###-#### Inspection requested via web by Kevin Perez...waiting on exterior light
|
Final | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PART |
Tom Saunders
|
|
|
Max Phone #: ###-####...partial final for new offices, bathrooms, and breakroom so staff may move in...remaining work is demo on existing building and new entry once built...can in soffit and outlet
|
Electrical Rough-In | 6/7/2018 | 6/8/2018 | 6/8/2018 | A | PASS |
Tom Saunders
|
|
|
Max Phone #: ###-####...ceiling grid -ok to cover
|
Electrical Rough-In | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PASS |
Tom Saunders
|
|
|
Max Phone #: ###-####...remaining walls and hard lids
|
Electrical Rough-In | 4/16/2018 | 4/17/2018 | 4/17/2018 | A | PASS |
Tom Saunders
|
|
|
Max Phone #: ###-####...walls and hard lid areas ok to cover...excluding staff lounge, lockers area, and charting area
|
Issue PAID IN FULL permit | | | 3/14/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/14/2018 | | DONE |
|
|
|
This permit was created on the web by Kevin Perez
|
First Notice | 10/30/2018 | 10/30/2018 | | | |
Tom Saunders
|
|
|
|