Final | 5/7/2018 | 5/7/2018 | 5/7/2018 | A | PASS |
Eric Story
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (###-####) one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Final ok
|
Electrical Rough-In | 4/30/2018 | 5/3/2018 | 5/3/2018 | A | PASS |
Eric Story
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Verified U/L listing and scope of work for Solar Array install all looked good to proceed.
|
Issue PAID IN FULL permit | | | 3/23/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/23/2018 | | DONE |
|
|
|
This permit was created on the web by Rob Maes
|