First Notice | 8/13/2018 | 8/13/2018 | 8/31/2018 | | DONE |
Daryl DeGrange
|
|
|
This permit finaled on the web by Scott Campbell
|
Final | 8/9/2018 | 8/13/2018 | 8/13/2018 | P | PASS |
Daryl DeGrange
|
|
|
Please Call 30 minutes ahead of inspection for escort Phone #: ###-#### Inspection requested via web by Scott Campbell Correction complete, Final ok
|
Final | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | FAIL |
Rock A. Hudson
|
|
|
Please call 30 to 60 minutes before inspection so we can provide an escort for inspection. Phone #: ###-#### Inspection requested via web by Scott Campbell 110.7- Wires pinched by ballast cover in reception area. 300.11- Speakers shall be supported independant of grid as per Dave Hanna. 314.25- All boxes containing a splice shall have a cover. Reception area. 400.12- Flexible cords shall not penetrate or run above ceiling grid. Projector. As noted on print 2012 IECC shall comply. Dual switching as noted on print shall reduce loads by at least 50%. Intern area 3-1, offices 2-0, conference room lighting most not working, Reception area OK.
|
Electrical Rough-In | 5/25/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Daryl DeGrange
|
|
|
James Lingelbach Reception area Rough-in Phone #: ###-#### Inspection requested via web by Scott Campbell rough-in ok cover walls in reception area
|
Electrical Rough-In | 5/16/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Daryl DeGrange
|
|
|
Contact - James LIngelbach Phone #: ###-#### Inspection requested via web by Scott Campbell rough-in ok cover walls except reception area
|
Issue PAID IN FULL permit | | | 4/5/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/5/2018 | | DONE |
|
|
|
This permit was created on the web by Scott Campbell
|