Final | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | PASS |
Eric Story
|
|
|
Partial electrical final for Units : 201, 202, 204, 240, 241, and 101 Contact : David Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Harvey Reyna Final ok
|
Final | 12/4/2018 | 12/5/2018 | 12/5/2018 | A | FAIL |
Eric Story
|
|
|
Partial electrical final for Units : 201, 202, 204, 240, 241, and 101 Contact : David Phone #: ###-#### Inspection requested via web by Harvey Reyna 406.9 Tamper esisitant required in apartments(bath and Kitchen)
|
Final | 12/4/2018 | 12/5/2018 | 12/4/2018 | A | CANC |
Eric Story
|
|
|
Partial Final for Units 201,202,204,240,241 Contact: David Phone #: ###-#### >> Inspection requested via web by Harvey Reyna Inspection cancelled from web by: Harvey Reyna
|
Final | 12/4/2018 | 12/5/2018 | 12/4/2018 | A | CANC |
Eric Story
|
|
|
Contact David Partial electrical final Phone #: ###-#### >> Inspection requested via web by Harvey Reyna Inspection cancelled from web by: Harvey Reyna
|
Electrical Rough-In | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PASS |
Eric Story
|
|
|
Request for electrical rough-in for unit 240. Contact Tod Lane Phone #: ###-#### Inspection requested via web by Harvey Reyna Unit 240 ok to cover
|
Electrical Rough-In | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | PASS |
Eric Story
|
|
|
Unit 240 ok to cover
|
Electrical Rough-In | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | FAIL |
Eric Story
|
|
|
Requesting an electrical rough-in for unit 240. Contact David: ###-#### Phone #: ###-#### Inspection requested via web by Harvey Reyna BCO it shall be unlawful to conceal any electrical install proir to inspection. Walls only will need to be removed as ceilings were looked at an another date(to much insulation in room to have inspected walls at that time)
|
Electrical Rough-In | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | PASS |
Tom Saunders
|
|
|
Inspection for units: 102, 104, 140, 141, 204 Phone #: ###-#### Inspection requested via web by Harvey Reyna...ok to cover 5 rms requested
|
Electrical Rough-In | 9/19/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Eric Story
|
|
|
Units 101, 142, 201, 202, 241 Phone #: ###-#### Inspection requested via web by Harvey Reyna Units as requested ok to cover
|
Final | 8/2/2018 | 8/3/2018 | 8/3/2018 | P | PART |
Eric Story
|
|
|
Dustin Palmer is the contact.
Requesting final inspection in order to receive a Temporary Occupancy on Phase One of the project.
Apartments 103, 106, 117, 118, 125, 134, 138, 205, 216, 237, 242 Phone #: ###-#### Inspection requested via web by Harvey Reyna Rooms as requested first 11 are ok to occupy at this time
|
Electrical Rough-In | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | PASS |
Eric Story
|
|
|
Remainder of Apartments: 125, 138, 205, 216, 237, 242 Phone #: ###-#### Inspection requested via web by Harvey Reyna Units where brick walls and framing not allowing of wall space receptacles to be placed are ok to not have them due to existing structure, if they can be added they will be. Units as described in request ok to cover
|
Electrical Rough-In | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Eric Story
|
|
|
Partial rough-in inspection on completed units 103, 106, 117 ; 118. Phone #: ###-#### Inspection requested via web by Harvey Reyna Units as requested and 134 ok to cover, wall between some untis is existing brick and no way to maintian 6' spacing, being a existing application spacing seemed ok to proceed
|
Issue PAID IN FULL permit | | | 5/30/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/30/2018 | | DONE |
|
|
|
This permit was created on the web by Harvey Reyna
|