Print Statement | | | 8/15/2019 | | DONE |
|
|
|
|
Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Eric Story
|
|
|
Re-inspect for final. Phone #: ###-#### Inspection requested via web by Bryan Atkins Occ card not on site Corrections fixed final ok
|
Conference | 1/30/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Rock A. Hudson
|
|
|
After discussing building type use, as per Daryl DeGrange GFCI protectoin of two 50 amp receptacles not required
|
Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins 110.3- GFCI on north wall will not trip. 210.8- Single phase up to 50 amp and 3- phase receptacles up to 100 amp 150 volts to ground or less shall have GFCI protection. Welder and plasma. 330.30- MC cable shall be secured with in 12" of boxes other than fixture whips. North door opener. 400.5- 6-3 flexible cords with 3 current carrying conductors ampacity shall not exceed 45 amps. Welder and plasma. 400.12- Flexible cords shall not be run thru walls, floors, or ceilings. Remove temp lighting cords and one cord from level 1 to mezz for fan.
|
Electrical Rough-In | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | PASS |
Eric Story
|
|
|
Rough-in under mezzanine Phone #: ###-#### Inspection requested via web by Bryan Atkins Mezzanine only ok to cover conduit in hard lid, remaining to be surface mounted....
|
Electrical Rough-In | 11/2/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins Bathroom rough in ok cover
|
Permanent Service | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins 120.24 AFC calc required proir to service being energized
|
Electrical Rough-In | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Rock A. Hudson
|
|
|
Electrical Underground Rough-In Phone #: ###-#### Inspection requested via web by Bryan Atkins Underground 2- 1" from building to gate rough in ok cover
|
Electrical Rough-In | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | PASS |
Tom Saunders
|
|
|
Uffer Ground Phone #: ###-#### Inspection requested via web by Bryan Atkins...ok to cover
|
Electrical Rough-In | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Eric Story
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Bryan Atkins u/g ok to cover
|
Electrical Rough-In | 6/11/2018 | 6/12/2018 | 6/12/2018 | A | FAIL |
Eric Story
|
|
|
Underground secondary and security gate. Phone #: ###-#### Inspection requested via web by Bryan Atkins u/g needs to be 24"
|
Issue PAID IN FULL permit | | | 6/11/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/11/2018 | | DONE |
|
|
|
This permit was created on the web by Bryan Atkins
|
First Notice | 1/30/2019 | 1/30/2019 | | | |
Eric Story
|
|
|
|