Print Statement | | | 11/20/2018 | | DONE |
|
|
|
|
First Notice | 8/28/2018 | 8/28/2018 | 8/28/2018 | | DONE |
James Ady
|
|
|
This permit finaled on the web by Stacie Tasker
|
Final | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PASS |
James Ady
|
|
|
For Site Bldg B ; C, Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker final ok
|
Electrical Rough-In | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
James Ady
|
|
|
We need an underground inspection for Site at B ; C. Jeff is the site contact, Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker underground only ok to cover
|
Electrical Rough-In | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Eric Story
|
|
|
We need and underground for the Site. Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker GC difficult to work with, was angry about no hard hat when there was no sign stating it was required. U/G for lighting
|
Issue PAID IN FULL permit | | | 6/13/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/13/2018 | | DONE |
|
|
|
This permit was created on the web by Stacie Tasker
|