Final | 8/5/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Tom Saunders
|
|
|
I completed this work on Friday afternoon, bonding the bushing inside the breaker panel, and installing the intersystem bonding termination. I can text pictures, or I can meet there to open the panel, just let me know in plenty of time to get there (I expect to be at the base of Bogus Basin Rd.) Let me know what you''d like and I will accomodate. Thanks ~ Dan Phone #: ###-#### Inspection requested via web by Dan Hilke... corrections made...ok to final
|
Final | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | FAIL |
Rock A. Hudson
|
|
|
Just call before you get there and I''ll meet you so I can remove the panel cover for you. Phone #: ###-#### Inspection requested via web by Dan Hilke 250.92- Metal nipple entering thru concentric KO from meter shall have a bonding bushing bonding complete. Bonding bushing installed, no lug on bonding bushing. 250.94- Bonding strap installed on service lateral riser, informed a llisted intersystem bond bar shall be installed. 2 ground rods installed on fence line, rest of corrections ok.
|
Permanent Service | 8/2/2018 | 8/2/2018 | 8/2/2018 | P | PASS |
Rock A. Hudson
|
|
|
Just call before you get there and I''ll meet you so I can remove the panel cover for you. Phone #: ###-#### Inspection requested via web by Dan Hilke p/s u/g rec ok
|
Final | 7/31/2018 | 7/31/2018 | 7/31/2018 | P | NR |
Tom Saunders
|
|
|
This is for changing out an old panel. It''s in back corner of the garage. I live nearby, please call when you''re on your way and I should be able to meet you there. Thanks ~ Dan Phone #: ###-#### Inspection requested via web by Dan Hilke... ID Power turned power on before perm service inspection scheduled...job completed past 5 pm...temped in service to get power back on...few additional requirements need done before can final multiple branch circuits in panel need to be on 2 pole breaker grounding needs brought up to code-2 rods intersysytem bond needs installed platform will be installed to satisfy highest breaker highth code requirement romex under panel needs fixed to code with outside outlet as well...romex protected from physical damage and exterior outlet needs GFI protection, W/R outlet and inuse H/D cover
|
Issue PAID IN FULL permit | | | 6/18/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/18/2018 | | DONE |
|
|
|
This permit was created on the web by Dan Hilke
|