First Notice | 9/11/2018 | 9/11/2018 | 9/12/2018 | | DONE |
Mark Moncarr
|
|
|
|
Print Statement | | | 9/12/2018 | | DONE |
|
|
|
|
Final | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
Mark Moncarr
|
|
|
830am. Dustin ###-#### Ok final. A few tables no power. Everything is plug and play. Waiting for pigtails to energize.
|
Final | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | CANC |
Mark Moncarr
|
|
|
Dustin is the site contact. Phone #: ###-#### Inspection requested via web by Kerri Hamilton Re-scheduled for 9/10/18
|
Electrical Rough-In | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...ceiling grid complete
|
Electrical Rough-In | 8/27/2018 | 8/28/2018 | 8/28/2018 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Team rooms @ phone room suspended ceilings only ok to cover
|
Electrical Rough-In | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok cover ceilings phone rm at entry, and 5 offices S side.
|
Electrical Rough-In | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PART |
Rock A. Hudson
|
|
|
Above ceiling grid inspection. Dustin is the contact at ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Kerri Hamilton South cloud only rough in ok cover
|
Electrical Rough-In | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PART |
Tom Saunders
|
|
|
ceiling rough-in above grid. Dustin is the site foreman Phone #: ###-#### Inspection requested via web by Kerri Hamilton...entry "cloud" cover only
|
Electrical Rough-In | 7/17/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Ok cover 3 cans 2 pendants in brkroom, and 4 cans in lobby area.( secondary entrance).
|
Electrical Rough-In | 7/6/2018 | 7/9/2018 | 7/9/2018 | P | PASS |
Rock A. Hudson
|
|
|
Dustin is our site foreman. 30 minute call ahead will be greatly appreciated Phone #: ###-#### Inspection requested via web by Kerri Hamilton No soffits, all walls rough in ok cover
|
Electrical Rough-In | 7/6/2018 | 7/6/2018 | 7/6/2018 | P | CANC |
Tom Saunders
|
|
|
Dustin is our foreman onsite. 30 minute call ahead would be appreciated Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|
Electrical Rough-In | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PART |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton North and west exterior walls only rough in ok cover
|
Conference | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...discussed existing circuits and pipes that are attached to roof deck, oked to leave, not pulling new circuits in them, using them for existing heating units...conference rm layout, # outlets, location, and floor outlet requirement...tie wire marking and number on lighter LED fixtures
|
Issue PAID IN FULL permit | | | 6/27/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/27/2018 | | DONE |
|
|
|
This permit was created on the web by Kerri Hamilton
|