Final | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | PASS |
Eric Story
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or Barry (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Fianl for solar array ok
|
Electrical Rough-In | 8/8/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Tom Saunders
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Request coincide this inspection with Service Upgrade Permit # ELE18-03002 Rough In. Thank you. Inspection requested via web by Rob Maes...
UL listed equipment verified...new equipment ok
|
Electrical Rough-In | 7/27/2018 | 7/30/2018 | 7/30/2018 | P | CANC |
Tom Saunders
|
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. >> Inspection requested via web by Rob Maes Inspection cancelled from web by: Rob Maes
|
Issue PAID IN FULL permit | | | 7/3/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/3/2018 | | DONE |
|
|
|
This permit was created on the web by Rob Maes
|