First Notice | 9/21/2018 | 9/21/2018 | 12/31/2018 | | DONE |
Eric Story
|
|
|
|
Print Statement | | | 12/31/2018 | | DONE |
|
|
|
|
Final | 9/20/2018 | 9/21/2018 | 9/21/2018 | A | PASS |
Eric Story
|
|
|
Contact: Tom Hartung Phone #: ###-#### Inspection requested via web by Deb Gooden Occ card on site and signed off for electrical, Final ok
|
Permanent Service | 7/25/2018 | 7/26/2018 | 7/26/2018 | A | PASS |
Eric Story
|
|
|
Contact: Tom Hartung Phone #: ###-#### Inspection requested via web by Deb Gooden AFC is 32,741 and breaker is rated at 65,000 p/s u/g n ok
|
Conference | 7/6/2018 | 7/9/2018 | 7/9/2018 | A | DONE |
Eric Story
|
|
|
Contact: Tom Hartung Phone #: ###-#### Inspection requested via web by Deb Gooden Discussed wiring in panelboard for bending radius and trip setting on breaker
|
Issue PAID IN FULL permit | | | 7/6/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/6/2018 | | DONE |
|
|
|
This permit was created on the web by Deb Gooden
|